Living Construction Projects Purple Line Extension Information
Purple Line Extension Information

 Metro Banner

 Purple Line Extension Project   EventsConstructionLinks | Documents

Contact Metro

24/7 Hotline:  213.922.6934 

Email | Facebook | Twitter

Sign up to receive constructions notices via email

Weekly Update
_____________________________________________________________________________________________

Wilshire Blvd. Weekend Closures Resume Nov 17 – 20 and Geotechnical Boring Work to Begin Nov 27

Wilshire/Rodeo Station

Weekend closure of Wilshire Boulevard between La Cienega and San Vicente and lane restrictions will resume November 17 – November 20. The detours for weekend closures are depicted in the map below.

East west detour map

Wilshire/La Cienega Station

Geotechnical work slated for Nov 13 has been delayed until after Nov. 27. Watch our Weekly Updates for details of upcoming work locations and schedule.

Geotechnical Boring work will gather additional soil information, which will help with subsurface station design and tunnel construction. Work will occur at multiple locations along Wilshire Boulevard between 8 p.m. to 6 a.m. on weekdays only.

Lane reductions will be required. 

______________________________________________________________________

Upcoming Events

Purple Line Extension Section 1: Construction Community Meeting

When: 

Thursday, November 16, 2017 from 6pm – 7:30pm

Where

John Burroughs Middle School (600 South McCadden Place, Los Angeles, CA 90036)

Description

Section 1: Construction Community Meeting

 

Sections 1 and 2: La Cienega Station and Rodeo Station Monthly Update Meeting

When

Wednesday, December 13, 2017 from 6:30pm – 8pm

Where

Beverly Hills City Hall (455 North Rexford Drive, Beverly Hills, CA 90210)

Description

This is a series of monthly meetings for Beverly Hills stakeholders interested in Metro construction and pre-construction for the Wilshire/La Cienega and Wilshire/Rodeo Stations in Beverly Hills. 

Additional information can be found in https://www.metro.net/projects/westside/events/

____________________________________________________________________

Construction Information

WILSHIRE BOULEVARD DECKING CLOSURES

 Wilshire Boulevard will be closed off entirely for decking and completion of piling during 17 weekends starting September 8 through February 2018.  

  • Detours are anticipated on La Cienega Boulevard between Olympic Boulevard and Third Street and on Wilshire Boulevard between San Vicente Boulevard and Doheny Drive with traffic officer support (See Phase 1, 2 and 3 Detour Maps)
  • Local access will be maintained for businesses and residents throughout the work zone
  • Pedestrian access will be maintained with sidewalk and crosswalk detours on La Cienega Boulevard and Wilshire Boulevard
  • Bus Stops
    • The 20 and 720 buses remain relocated to eastbound at Wilshire Boulevard near Stanley Drive and westbound at Wilshire Boulevard near San Vicente Boulevard
    • The 105 and 705 buses are relocated for the next eight to ten months to northbound La Cienega Boulevard and Gregory Way

What is Decking?

Decking is temporary roadway installed during construction that will allow for station construction underneath traffic.

What is Piling?

Piling, now underway, is the process of installing steel beams to structurally support the decking and station construction. The piling on the south side of Wilshire Boulevard is complete and the north side of Wilshire Boulevard is underway.

Work Schedule, Detours and Access During Weekend Closures*

  • Full street closures for 17 weekends starting September 8, 2017
  • Work will be continuous from Friday at 8:00 pm until Monday at 7:00 am
  • No work will take place on major holiday weekends, which include Rosh Hashanah (Sept. 23 - 24), Yom Kippur (Sept. 30 - Oct. 1), Veterans Day, Thanksgiving, Christmas, New Years, and President's Day

 

Phase 1: Piling across Wilshire Boulevard Completed

Full closure from San Vicente Boulevard to La Cienega Boulevard See: Phase 1 Proposed Eastbound / Westbound Detour Map

Phase 2: Decking Completed

Full closure of Wilshire Boulevard from San Vicente Boulevard to La Cienega Boulevard

See: Proposed Eastbound / Westbound Detour Map

Phase 3: Decking November 3-6, 17-20

December 1-4, 8-11, 15-18

January 5-8, 13-15, 19-22, 26-29

February 2-5, 9-12

Full closure of Wilshire Boulevard from San Vicente to La Cienega Boulevard See: Phase 3 Proposed Eastbound / Westbound Detour

____________________________________________________________________

Links

Metro Notice

Safety Tips

Metro Bus and Rail Schedules

Business Interruption Fund

Purple Line Extension Project Details

 _____________________________________________________________________________________________

Documents and Presentations

 

Chamber Government Affairs Committee August 2017

 

Metro Presentation July 2017 - Section 1 Construction Community Meeting

 

Metro Presentation June 2017 - Section 2 Pre-Construction Community Meeting

 

Chamber of Commerce May 2017 Meeting

 

Community Meeting Presentation February 2017

 

Community Meeting - January 2017

 

Metro Presentation November 2016 - Section 1 Construction Community Meeting

 

Metro Presentation October 2016 - Section 2 Pre-Construction Community Meeting

 

Metro Presentation August 2016 - Purple Line Extension Community Meeting:

 

City Presentation August 2016 - Purple Line Extension Community Meeting

 

Community Meeting Presentation November 2015

 

Purple Line Advanced Utility Relocation Memorandum of Agreement

 

Additional Resources

 _____________________________________________________________________________________________

Transportation and Parking
For public transportation use the Trip Planner at metro.net or call 323.go.metro. Two-hour free parking is available at the Civic Center Garage located at 450 N. Rexford Dr.

station map

 _____________________________________________________________________________________________

BUSINESS RESOURCES

Metro Business Interruption Fund (BIF) information and additional resources for your business.  

 _____________________________________________________________________________________________

The Purple Line Extension will provide a transportation alternative to the congested Westside, including two stops in Beverly Hills: Wilshire/ La Cienega and Wilshire/ Rodeo.

station map

 _____________________________________________________________________________________________

PROJECT DETAILS - Purple Line

The project is scheduled to be built in three sections.  The first section of the Purple Line Extension will extend the subway from the Wilshire/ Western station in Los Angeles to Wilshire/La Cienega in Beverly Hills.  Section 2 extends from the Wilshire/ La Cienega station to the Wilshire/ Rodeo station and then on to the Century City / Constellation station. 

Metro Purple Line Extension | Project Update from Beverly Hills Television on Vimeo.