Purple Line Extension Information

 Metro Banner

 Purple Line Extension Project   EventsLinks | Documents

Contact Metro

24/7 Hotline:  213.922.6934 

Email | Facebook | Twitter

Sign up to receive constructions notices via email

Weekly Update 08/17/18

Wilshire/La Cienega Station

Street closures scheduled for westbound Wilshire next two weekends.

The following closures are planned for the next two weekends, August 18-19 and August 25-26.* The closures will start Saturday at 3 am and last until Sunday at 9 pm.* Only local access for residents and entrance to businesses will be maintained:

  • Westbound Wilshire Boulevard will be closed from La Cienega Boulevard to Stanley.
  • North Le Doux will be closed at Wilshire Boulevard. Flaggers will be on site to assist with access to local businesses.  

Weekday closures* include the following:

  • Eastbound Wilshire Boulevard will be reduced to one lane from Hamel to La Cienega from 9 am to 3:30 pm.
  • Westbound Wilshire Boulevard will be reduced to one lane from Hamilton to Hamel from 9 am to 3:30 pm. The westbound closure will not happen at the same time as the eastbound closure listed above.
  • North Gale Drive will be closed from 7 am to 4 pm.

Please use alternative routes and continue to respect construction barriers and detours for your safety.

 Metro Map 6-26-18

Wilshire/Rodeo Station

Barriers moving to north side of Wilshire for utility relocation work.

Workers are in the process of moving the sidewalk barrier and k-rail to the north side of Wilshire Boulevard between Beverly Drive and N. Canon. The reinstallation is expected to be completed by Monday, August 20.*

Utility relocation work is expected to resume behind the relocated barriers on Tuesday, August 21.* Work hours are Monday through Friday, 7 am to 7 pm, and Saturday and Sunday from 10 am to 6 pm.*

Wilshire Boulevard between El Camino Drive and Canon Drive will be reduced to two lanes in each direction at all times. Right turns from westbound Wilshire onto Beverly Drive will not be permitted. Closure and detour signage will be posted. Traffic control officers or flaggers will be on site as needed.

Abatement and demolition preparations continue at former Ace Gallery building.

Workers continue to prepare the property for demolition. Abatement is expected to be completed in late August.* The demolition activities will begin once abatement is completed. Work hours are Monday through Friday, 8 am to 6 pm.* Hauling and heavy demolition activity can only take place between 9 am and 4 pm.*

When demolition starts, a portion of the park at 125 S. Reeves Drive will be closed and access will be restricted.

*Due to the dynamic nature of construction the schedule and activities may vary.

Be heard, complete the Metro Public Engagement Survey

Metro is conducting a public engagement survey to learn the best ways to communicate with you. Complete the survey here: https://www.metro.net/projects/westside/public-engagement-survey-beverly-hills/

 

______________________________________________________________________

Upcoming Events

Sections 1 and 2: La Cienega Station and Rodeo Station Monthly Update Meeting

When

Wednesdays in 2018: Sept 5, Oct 3, Nov 7, Dec 5

Time:

6:30pm – 8pm

Where

City Hall, Municipal Gallery (455 North Rexford Drive, Beverly Hills, CA 90210)

Description

This is a series of monthly meetings for Beverly Hills stakeholders interested in Metro construction and pre-construction for the Wilshire/La Cienega and Wilshire/Rodeo Stations in Beverly Hills. 

Upcoming City Council Meetings (Metro Items on Agenda):

When

August 21 - Section 2 MOA for Consideration

Time:

7pm, Formal Session

Where

City Hall, Council Chambers (455 North Rexford Drive, Beverly Hills, CA 90210)

Detailed City Council packets will be available prior to each meeting and can be found on http://www.beverlyhills.org/living/citycouncilmeetings/

Additional information can be found in https://www.metro.net/projects/westside/events/

____________________________________________________________________ 

Links

 

For the latest Metro Presentations, please click this link below and select “Section 1&2: City of Beverly Hills Presentations:”

Metro Presentations

Metro Notice

Safety Tips

Metro Bus and Rail Schedules

Business Interruption Fund

Purple Line Extension Project Details

 _____________________________________________________________________________________________

 

Documents and Presentations

 

Proposed Memorandum of Agreement Section 2

 

Purple Line Memorandum of Agreement Section 1

 

Draft: Purple Line Memorandum of Agreement - Section 2

 

Purple Line Advanced Utility Relocation Memorandum of Agreement

 

Additional Resources

 _____________________________________________________________________________________________

Transportation and Parking
For public transportation use the Trip Planner at metro.net or call 323.go.metro. Two-hour free parking is available at the Civic Center Garage located at 450 N. Rexford Dr.

station map

 _____________________________________________________________________________________________

BUSINESS RESOURCES

Metro Business Interruption Fund (BIF) information and additional resources for your business.  

 _____________________________________________________________________________________________

The Purple Line Extension will provide a transportation alternative to the congested Westside, including two stops in Beverly Hills: Wilshire/ La Cienega and Wilshire/ Rodeo.

station map

 _____________________________________________________________________________________________

PROJECT DETAILS - Purple Line

The project is scheduled to be built in three sections.  The first section of the Purple Line Extension will extend the subway from the Wilshire/ Western station in Los Angeles to Wilshire/La Cienega in Beverly Hills.  Section 2 extends from the Wilshire/ La Cienega station to the Wilshire/ Rodeo station and then on to the Century City / Constellation station. 

Metro Purple Line Extension | Project Update from Beverly Hills Television on Vimeo.